Crude units to be shut by Formosa for maintenance turnaround
:: 6 Aug 2013 ::
Formosa Petrochemical is in plans to shut two crude units for maintenance at its Mailiao refinery.
A Polymeurpdate source in Taiwan informed that an 80,000 bpd vacuum distillation unit (VDU) and 84,000 bpd residual fluid catalytic cracking unit (RFCC) are planned to be taken off-stream. The units are likely to be shut in October 2013. They are expected to remain off-stream for around three weeks.
The Mailiao refinery in Taiwan operated by Formosa Petrochemical has a crude processing capacity of 540,000 bpd.
More stories from POLYMERUPDATE
|